Located in Lilliwaup, Washington

News and Information

Moving Forward

On June 11, 2014

Completion of the cost estimate and finalization of the construction agreement are scheduled for June 30. Construction is set to begin Monday, July 7, 2014.


Final drawings for the landslide repair are being updated and will be submitted for the landslide area grading permit this week.


Work on Generators Begins…

On June 9, 2014

The initial work on the seven generators in the plant house has begun. Four generators and turbine bearings have been pulled from the plant house and taken to Aberdeen, Washington, where a company specializing in generator repair will be cleaning and refurbishing them.